Week of June 25th – Mobilization to the site, erosion control, signage, and layout
Week of July 1st – Mill existing pavement
Week of July 16th – Shim and pave roadway
Week of July 23rd – Striping of roadway and paving side streets and driveways
Week of July 30th – Demobilization
During night time hours the contractor will be using alternating one way traffic to move traffic around the work zone, the contractor will notify the comm. center prior. to implementing lane closures. This work is weather dependent and additional information will be provided as the work progresses.
Any inquiries regarding this project may be directed to the attention of Ryan Barnes, Project Manager, City of Lewiston, Public Works Department, Engineering Division, Telephone (207) 513-3003.