Augusta, Maine - As crews continue re-constructing Exit 113 in Augusta, a new paving schedule and detour routes will be in place for Wednesday, October 2nd and Thursday, October 3rd.

From 9:00 a.m. to 3:30 p.m. each day, the Exit 113 I-95 northbound entering traffic will be detoured from the intersection of Route 104 (West River Road) and Route 3 north along Route 104 to Lyons Road in Sidney to Exit 120.

The Exit 113 I-95 southbound entering traffic will be detoured from the intersection of Route 104 (West River Road) and Route 3 south along Route 104 to Old Belgrade Road to the Exit 113 southbound interchange I-95 south entering ramp.

Detour signs and variable message boards will be in place to alert and guide motorists for both days.

The Exit 113 Project will better enhance access to those traveling westerly and those going to the new regional hospital. Construction began in March and is expected to be completed in November.