Week of April 28th through May 4th
Beginning Tuesday night (April 30th), the contractor will begin milling operations on Main Street in Wiscasset. Milling will start at the bridge and proceed westerly to the end of the project. The contractor will mill the majority of the asphalt, leaving approximately one inch for drivers. Milling operations will continue on Main Street and Water Street (north) until this phase is complete; we expect this phase to take two or three days.
Week of May 5th through May 11th
Beginning on Sunday night (May 5th), the contractor will begin excavating Main Street. Crews will remove approximately two feet of dirt and replace it with new subbase gravel. The contractor will begin at the railroad tracks and proceed westerly. During the week, the contractor hopes to excavate from the railroad tracks to Walker Street. Excavation and gravel operations should happen on Sunday, Monday, and Tuesday nights. Fine grading is expected to happen on Wednesday night. Placement of the new asphalt base is expected to happen on Thursday night.
Week of May 12th through May 18th
During the week of May 12th, the contractor will continue the excavation of Main Street from Water Street to Middle Street. Excavation and gravel operations will happen on Sunday, Monday, and Tuesday nights. Fine grading will happen on Wednesday night. Asphalt base placement will happen on Thursday night.
Week of May 19th through May 25th
During the week of May 19th, the contractor will continue will the same procedure on Main Street from Middle Street to Federal Street and the end of the project.
Barring any bad weather, breakdowns, or unforeseen discoveries under the roadway, the Town of Wiscasset and the travelling public will have the first layer of new pavement in place on Main Street by Memorial Day weekend.